1 · Two routes
Transport rights or supplying flexibility?
The two routes are often confused, but work in fundamentally different ways.
Route 1 · Alternative transport rights
You accept less transport certainty
The contract determines when and how much you may transport. In return you pay a lower transport tariff and often get grid capacity sooner.
- TDTR
- TBTR
- VVTR
Route 2 · Congestion management
You supply flexibility to the grid
The contract determines how and when you adjust your power during congestion. You are paid for this.
- CSC-T
- CSC-A
- Bidding obligation
- Redispatch
2 · The contracts
How each contract works — in 12 seconds
Choose a contract and see how it works, who it is for and how you earn from it.
3 · Compare and earn
All contracts side by side
With transport rights you earn through a lower transport tariff, with congestion management through fees.
| Contract | What it means | For whom | Arranged via | Where | How you earn |
|---|---|---|---|---|---|
| TDTR | Full transport ≥ 85% of the time | Generation and offtake, also in queue | Grid operator (TenneT only) | Inside and outside congestion areas | No kW-contract + kW-max discount (up to 65%) |
| TBTR | Transport within fixed time blocks | Generation and offtake, also in queue | Grid operator | Inside and outside congestion areas | Discount on kW-contract |
| VVTR | Transport when spare capacity is available, no guarantee | Very flexible assets | Grid operator | Congestion areas | No kW-contract |
| CSC-T | Flexibility at fixed times | Generation and offtake, also in queue | Grid operator or CSP | Only within congestion areas | Availability fee + per MWh |
| CSC-A | Flexibility on call at peaks | Generation and offtake, also in queue | Grid operator or CSP | Only within congestion areas | Availability fee + per call + per MWh |
| Bidding obligation | Mandatory bidding on GOPACS | Above 1 MW, already connected | CSP | Inside and outside congestion areas | Availability fee + per MWh when accepted |
| Redispatch | Voluntary bidding on GOPACS | Above 1 MW, already connected | CSP | Inside and outside congestion areas | Per MWh when accepted |
Source: GOPACS product comparison; tariff discounts according to ACM, TenneT and RaboResearch (2025). Exact fees differ per grid operator and contract.
4 · Market in figures
Alternative transport rights are scaling up fast
By the end of 2025, 162 contracts were active, mostly TBTR. Flexible grid use is becoming common practice, but further scaling is needed to really shorten the waiting lists.
TDTR at TenneT
More than 70 GW requested, 9.1 GW available. 57 companies were allocated capacity; by the end of 2025, 26 contracts had been signed, 10 of them active.
Active contracts, end of 2024 vs. end of 2025
- 2024
- 2025
- * TDTR in development
5 · Your business case
The contract alone does not tell the business case
Voltho Gridflow simulates per location and per hour when and how much transport capacity is available — for current and future grid situations.
01
How many hours and MW your project will be restricted
02
When these restrictions occur and why
03
Interaction with electricity and flexibility markets
04
Impact on uptime, revenue and business case